CSc 4350/6350 Software Engineering
Fall 1999
 
 
Dates Topics References Notes and Deliverables Chapters
Aug 23
25
27
What is SE?
Product
Process

P: 3 - 21
P: 22 - 26

Course Overview

Form Teams

1
2

Aug 30
Sep 1
3
Process Models
Management
Metrics I
P: 37 - 53
P: 57 - 75
P:76 - 101
  2
3
4
6
8
10
Labor Day
Planning
REVIEW I
P: 102 - 120  Select Projects 5
13
15
17
COCOMO
Risk Analysis
Scheduling
P: 120 - 131
P: 132 - 152
P: 153 - 178
 Team Description (1) 5
6
7
20
22
24
SQA
SCM
Sys. Engineering
P: 179 - 208
P: 209 - 227
P: 231 - 269
 

Exam 1 (Ch: 1-9)

8
9
10
27
29
Oct 1
Analysis
Modeling
REVIEW II
P: 270 - 297 11
12
 
4
6
8
Design I
Methods I
Methods II
P: 341 - 370
P: 371 - 395
P: 395 - 422
 System Definition (2) 13
14
14
11
13
15
RT Systems
Testing I
Testing II
P: 423 - 447
P: 448 - 486
P: 487 - 516
 

Exam 2 (10-17)
"W-Day"

15
16
17
18
20
22
Metrics II
Object-Oriented I
REVIEW III
P: 517 - 548
P: 551 - 580
 
18
19
 
25
27
29
OO II
OO III
OO IV
P: 581 - 613
P: 614 - 643
P: 644 - 663
Req/Spec (3) 20
21
22
Nov 1
3
5
OO V
Formal Methods
Cleanrooms
P: 664 - 677
P: 681 - 706
P: 707 - 727
  23
24
25
8
10
12
SW Reuse
Re-Engineering
REVIEW IV
P: 728 - 755
P: 756 - 783
 
26
27
 
15
17
19
Client/Server
CASE
The Future
P: 784 - 804
P: 805 - 825
P: 826 - 839
System Design (4)

Exam 3 (18-29)

28
29
 
22 Miscellaneous  
29
Dec 1
3
REVIEW IV
Presentations I
Presentations II
Test Plan (5)
User Manual (6)
 
 6
8
10
Presentations III
Presentations IV
Course Review
     
 
Dec. 13, Monday @ 10:15 a.m. FINAL EXAM

P = Pressman Software Engineering: A Practitioner's Approach (4th ed.)

 